On November 12, 2026, the 1,200 TPD active lime rotary kiln production line project of Hejin Kangzhuang New Materials Co., Ltd., with MER GROUP as the EPC general contractor, has reached the critical installation milestone of hoisting the large riding ring of the rotary kiln. Following multiple rounds of prior technical exchanges and scheme discussions, a full sequence of work including drawing design, equipment fabrication, precision machining, phased shipment and on-site installation has been completed in an orderly manner.

The riding ring serves as the core load-bearing component that supports stable rotation of the rotary kiln shell and demands extremely high machining accuracy. This riding ring was precision-turned on an 8-meter CNC vertical lathe at the MER GROUP plant. It passed multiple rigorous quality inspections and was delivered to the project site after all technical indicators met standards. At the hoisting site, construction crews carried out transportation and lifting operations methodically with precise control over hoisting posture. The riding ring will then be smoothly fitted onto the kiln shell for precise matching. This spectacular construction scene was vividly described by on-site staff as "a carp leaping over the dragon gate".
The successful completion of this riding ring hoisting milestone marks a major breakthrough in the installation of the project's main equipment. Going forward, the project team will push ahead with the construction schedule, strictly control quality and safety, steadily carry out subsequent installation procedures, and make every effort to ensure the early completion and commissioning of the production line.